When preparing a construction contract, the first step is to establish each party’s design responsibilities and ability to control the risks involved. This provides the basis for choosing a FIDIC form suited to the project’s delivery structure. Choosing an unsuitable form may require extensive amendments and make contract documentation harder to manage from the tender stage.
The Red Book is intended for works designed by the Employer; the Yellow Book for works designed and built by the Contractor; and the Silver Book for EPC/turnkey projects requiring greater certainty over price and completion. These distinctions reflect the structure of the FIDIC forms. The choice must nevertheless be assessed for each individual project. FIDIC Red Book, Yellow Book and Silver Book.
The role of FIDIC forms
FIDIC is the International Federation of Consulting Engineers, which develops standard conditions of contract for construction and agreements for consultancy services. The standard conditions become part of a contract when the parties select them and agree to apply them. The parties must also comply with the law governing the contract.
Article 34(3) of Decree 210/2026/NĐ-CP encourages reference to and use of standard forms developed by reputable professional associations such as FIDIC. For projects in Vietnam, the parties need to review and adapt the terms to comply with Vietnamese law. Decree 210/2026/NĐ-CP, Article 34.
Choosing a form based on design responsibility
The Red Book for Employer-designed works
The Red Book, officially titled Conditions of Contract for Construction, is designed for works where the Employer is responsible for the design. The Contractor may still undertake the design of certain parts of the works. The parties should clearly define that design scope in the contract documents. FIDIC Red Book 2017.
The Employer may consider the Red Book when it wishes to retain control over design decisions and has an appropriate project management organisation in place. Before issuing the documents, responsibilities should be allocated for incomplete drawings, coordination conflicts between disciplines and design changes. If the Contractor is to design a specialist system, the documents must separately specify that system’s scope of work and acceptance criteria.
According to FIDIC’s introduction to the 1999 Red Book, payments are normally determined by measurement and application of the rates and prices in the bill of quantities. The payment mechanism for an individual contract also depends on its valuation provisions and the amendments agreed by the parties. FIDIC Red Book 1999.
The Yellow Book for Contractor-designed works
The Yellow Book, Conditions of Contract for Plant and Design-Build, is intended for electrical and mechanical plant and for works designed by the Contractor. FIDIC Yellow Book 2017, reprinted 2022 with amendments.
Under this model, the Employer needs to define capacity requirements, output quality, operating standards, testing conditions and the boundaries of the scope of work. The Contractor needs the freedom to choose solutions that meet those requirements.
Where the Employer prescribes detailed design solutions, the contract should clearly allocate responsibility for their performance, even if the Contractor is responsible for design. The parties should compare the Employer’s Requirements with the Contractor’s technical proposal to identify and resolve inconsistencies before signing.
When to consider the Silver Book
The Silver Book, Conditions of Contract for EPC/Turnkey Projects, is intended to place responsibility for designing and executing the works with a single entity, for handover ready for operation. The Contractor assumes a wider scope of responsibility and risk than under traditional forms. According to FIDIC, greater price certainty comes with a risk contingency included in the tender price. The Employer needs to accept that contingency and enable the Contractor to assess the available information fully. FIDIC Silver Book 1999.
Before selecting the Silver Book, the parties need to assess the Contractor’s ability to quantify the risks allocated to it. FIDIC expressly states that the 2017 Silver Book is unsuitable where:
- The Contractor has insufficient time or information to scrutinise the requirements, carry out design, assess risk and prepare its price
- The works involve substantial underground work or areas that cannot be inspected, unless special provisions address unforeseen conditions
- The Employer intends to supervise closely, control the Contractor’s work or review most construction drawings
For Contractor-designed works in those circumstances, FIDIC recommends considering the 2017 Yellow Book. FIDIC’s guidance on when the Silver Book should be used.
Adequate site investigation data enables the Contractor to assess risk and commit to a fixed price. Where information is incomplete, the Employer should provide additional information, allow time for clarification or choose an appropriate risk-sharing mechanism.
Forms for specific requirements
For lower-risk works where the parties need simpler contract administration, the 2021 Green Book may be considered. FIDIC presents this edition as suitable for both Employer-designed and Contractor-designed works. FIDIC’s introduction to the Green Book 2021.
For consultancy services covering feasibility studies, design or contract and project management, the parties may use the 2017 White Book, a model services agreement between a client and a consultant. For projects requiring design, construction and long-term operation, the parties may consider the 2008 Gold Book under the design-build-operate (DBO) model. FIDIC developed this form for greenfield projects with a 20-year operation period. The operation period for each DBO contract should be determined by the project’s specific requirements. FIDIC White Book 2017, FIDIC Gold Book 2008.
Dredging, reclamation and ancillary construction works are covered by the Dredgers Contract, the 2016 Blue-Green Book. For projects financed by multilateral development banks, FIDIC offers the MDB Harmonised 2010 form, commonly known as the Pink Book. Its use must be consistent with the procurement documents and the funding institution’s requirements for the project concerned. FIDIC Dredgers Contract 2016, FIDIC MDB Harmonised 2010.
The applicable edition and amendments
The Red, Yellow and Silver Books each have a first edition published in 1999 and a second edition published in 2017. The 2022 version is a reprint of the second edition with amendments, titled “Second Edition 2017, Reprinted 2022 with amendments”. Red Book, reprinted 2022, Yellow Book, reprinted 2022, Silver Book, reprinted 2022.
The full name of the edition and the applicable amendments should be clearly stated in the contract documents. When handling notices, payments, extensions of time or disputes, contract administrators must refer to the agreed edition and the amendments applicable to the project. The conditions already agreed remain applicable when FIDIC publishes a new edition; adopting the new edition requires agreement between the parties.
Claims procedures, time limits and clause references must be consistent with the selected edition. If the parties wish to combine provisions from the 1999 and 2017 editions, they should expressly record their agreement and check the consistency of all related provisions.
General Conditions and Particular Conditions
The General Conditions contain FIDIC’s standard provisions. The Particular Conditions set out project data and amendments. Under the structure of the 2017 Red Book, Part A of the Particular Conditions contains the Contract Data and Part B contains the Special Provisions. FIDIC’s guidance requires amendments to the standard provisions to be set out in the Particular Conditions. The text of the General Conditions is protected by copyright; directly amending that text requires the appropriate consent or licence. FIDIC’s guidance in the Red Book 2017.
The FIDIC Golden Principles require the core characteristics to be preserved, including clarity in the Particular Conditions and the balance of risk allocation in the standard form. FIDIC Golden Principles 2019.
A schedule comparing the amendments should identify the basis for each change: a mandatory legal requirement, a technical feature or a commercial agreement. For each amendment, the parties need to identify its effect on price, insurance, security, notice periods and the dispute resolution mechanism.
A hypothetical example of form selection
Suppose a company plans to build a water treatment plant and appoints a Contractor to design and construct it. The company requires a guaranteed output capacity and is considering the Silver Book to control its budget. However, geotechnical data is incomplete, the pipeline route is still subject to change and the tender period allows only enough time to prepare a preliminary proposal.
These conditions limit the Contractor’s ability to assess and quantify risks before pricing. The company should consider the Yellow Book or complete the site investigations and define the scope before inviting tenders under the Silver Book. The final choice also depends on the Contractor’s ability to investigate the site, the Employer’s control over design and the change provisions in the contract documents.
Once the data is complete, output requirements are stable and the Contractor has time to assess them, the company may reconsider the Silver Book. The comparison should take account of tender prices, total costs and whether the proposed transfer of risk can be put into practice.
Documents to prepare
Before choosing a form, the parties should prepare a description of the scope of work, the status of design and site investigations, output requirements, the intended pricing basis, the programme, funding sources and any funding institution’s requirements. These documents provide the basis for allocating responsibilities, assessing whether risks can be priced and establishing a suitable project management organisation.
Once the form has been selected, the parties need to complete the Particular Conditions, align the technical appendices and administer the project in accordance with the signed contract.